Configuration

Configuration

This screen will allow you to set defaults and other settings for the Workforce Planning module.

General Setup

To start you must select the company codes and cost centers that will be included in Workforce Planning.

Step 1: Select the company codes to include
Step 2: Select the cost centers to include
Step 3: Select the Cost Types to include and assign to a category (Employee, Equipment, Sub)

These setting will filters the jobs that appear in the planning system.

Calendar Settings

Set the calendar that you wish to use for holidays.  These dates will be blocked out in the scheduling system.  Only one calendar can be assigned.  You can adjust the holidays by clicking the OPEN CALENDAR SETUP button.  Follow the help on that screen.

Set the default work week, start and finish times for your company.  Individual jobs and assignments can over-ride these settings if required.

Information Settings

When you drag a job onto the schedule, the system will copy data onto the assignment.  Set the data that you wish to copy onto the job:
Job Number
Job Name
Phase Code
Phase Description

The checked items will be copied onto the assignment and appear as follows:
Job Number: Job Name
Phase Number: Phase Description

Job Dates: Set if you want to lock dates to the ERP system dates or allow users to edit.

Color Settings

Assignment Colors

You can set the color you would like for various conditions in the system:
No Constraints - these are assignments on jobs where you have not set any specific constraints.
Constraints - assignments for jobs that have a setting for Must Start On or Must Finish On specific dates.
Approved Time Off - this is future
Conflict - assignments that are overlapping for a resource

Title Colors

You can assign colors to various job titles.  Click the UPDATE button to refresh the list.  This will find all the job title being used in your ERP system.  Some titles may not be of interest so set them WHITE.

Setting these colors will display a color bar next to the employee name on the resource list.  

Office Addresses - Future
    • Related Articles

    • Job Configuration

      The purpose of this screen is to allow users to: Assign a master phase code structure to a job.  This parses the phase code with readable descriptions. Add additional users to the job.  The system automatically gives permission to the PM, Super and ...
    • Time Entry Configuration

      This screen allows you to control the configuration settings for the time entry module. Time Entry Overview There are 3 methods for entering time cards: Regular users can use the main JobSiteForecast application at URL app.jobsiteforecast.com. Mobile ...
    • Add/Remove a Cost Center

      You can control which cost centers are included or excluded in JobSiteForecast. To adjust the cost centers: From the main menu select SETUP, then COMPANY SETUP On the setup panel under Cost Centers, add or remove cost centers as appropriate. You can ...
    • Time Card Approvals

      This screen provides a way for users to approve timecards. Access to this screen is controlled by permissions. The system will flag timecards for any employee that is set with a supervisor code. These time cards appear highlighted with a light yellow ...
    • Give a User Permission to a Job

      The accounting system has a field for the following people on a job: Project Manager Super Estimator These people are transferred from the accounting system and will automatically be given permission for that job, as long as they are users in the ...