Release Notes - July 2023

Release Notes - July 2023

Cost Analysis Screen

This screen now provides the ability to edit the Projected Cost JSF and push the updated projection back into Spectrum.  For details on how to use this new feature, read the article on Job Cost Analysis.

Look Ahead Plan Screen

In addition to Man Weeks Remaining, we have added a column Hours Remaining.  
Similarly, in addition to Man Week Balance, we have added Hours Balance.
Users may want to hide one set of columns and save their view.

Disengage Gantt Schedule selection is now available.  When this is checked, the system then allows you to enter your own Scheduled Start and Scheduled Finish Dates.  Unchecking this will revert back to using the Scheduled Dates from the Gantt Schedule.  

Schedule Screen

You can now IMPORT DATES from Spectrum while on the schedule screen. 

Cost Summary Screen

Highlighting has been added to the Projected Cost JSF similar to the Job Cost Analysis screen.  When the Projected Cost ERP is different from the Projected Cost JSF, that field will be highlighted RED.

Job Trend / Phase Code Trend

We have added another option to the graphs so now you can select Projected Cost Over (Under).